School Construction

At the Greater Essex County District School Board (GECDSB), we are committed to updating our school facilities to create sustainable and safe learning and working environments for students, staff and community partners.

View School Renewal Investment Report

View each of our current construction projects and get project updates and completion timelines.

 Current Projects

Forest Glade Public School (Renovation) 

Not Capital Priority Funding, Funding will be through School Conditioning Funding

  • Grant: N/A – Approx. construction cost $16,000,000
  • Pupil Places: 706
  • Architect: Archon
  • General Contractor: Alliance General Contracting
  • Construction commenced January 2025
  • The project is anticipated to be complete in July 2026, allowing the students to return for the start of school in September 2026.

 

 Roseland Public School (Addition) 
  • Grant: $3,913,731
    • Additional Funding: $440,645
    • Total Funding: $4,354,376
  • Pupil Places: 184 (8 Classrooms)
  • Architect: Architecttura Inc.
  • General Contractor: Sterling Ridge Group Inc. 
  • Construction commenced March 2025
  • Occupancy: Opening of the addition is anticipated in September 2026.
  • Roseland Addition Rendering
 Glenwood Public School (Addition) 
  • Grant: $3,707,933
    • Additional Funding: $218,520
    • Total Funding: $3,926,513
  • Pupil Places: 184 (8 Classrooms)
  • Architect: Architecttura Inc.
  • General Contractor: Sterling Ridge Group Inc. 
  • Construction commenced March 2025
  • Occupancy: Opening of the addition is anticipated in September 2026.
  • Glenwood addition rendering
 Lakeshore (New School)
  • Grant: $13.02 million
  • Pupil Places: 582
  • Location: East of Rourke Line Road and North of Girard Drive
  • Architect: Architecttura Inc.
  • General Contractor: T.B.D.
  • Construction commenced March 2025 (Target Date)
  • Occupancy: September 2027 (Target Date)

 New Lakshore School Rendering

 Completed Projects

  Queen Elizabeth Public School (Addition)
  • Grant: $8,147,057
  • Pupil Places: 78
  • Architect: Architecttura Inc.
  • General Contractor: Alliance General Contracting
  • Construction commenced July 2024
  • The FDK addition was completed in June 2025 and the Daycare and the retrofit area were completed in September 2025.

Queen Elixabeth Addition Rendering

Northwood Public School (Addition)
  • Grant: $4,854,477
  • Pupil Places: 184 (8 classrooms)
  • Architect: Cornerstone Architecture
  • General Contractor: Titan
  • Construction commenced July 2024
  • The addition opened September 2025

Northwood Addition rendering

Beacon Heights Public School 

In November 2015, the Greater Essex County District School Board (GECDSB) was awarded a grant of $15.3 million for the construction of a new school in Tecumseh. In 2022 the GECDSB was awarded an additional $7.2 million for this project. This new school will replace the current D.M. Eagle Public School and serve students from Kindergarten to Grade 8 within the Tecumseh and Lakeshore areas.

  • ​Grant: $22,500,000
  • Pupil Places: 651
  • Architect: J.P. Thomson
  • General Contractor: Fortis Group
  • Construction Begins: 2022
  • Final Completion: September 2024

Beacon Heights Exterior

Erie Migration District School K-12 

The Greater Essex County District School Board has purchased land to develop a new Kindergarten to Grade 12 school in Kingsville. The new school will replace Kingsville District High School, Kingsville Public School and Jack Miner Public School.

  • Grant: $59,900,000 (approximately)
  • Number of students: 1,045 elementary students and 753 secondary students
  • Architect: Architecttura
  • General contractor: Fortis Construction
  • Construction begins: April 2022

Final completion: September, 2024Erie Migration Exterior

Eastview Horizon Public School 

Eastview Horizon Public School consolidated Eastwood and Parkview Public Schools.

Construction for the new school began in May of 2021. There were some unavoidable delays with the project and the timeline for completion was adjusted. We opened the school in September, 2023.

  • ​​​Grant: $11,080,000 plus $2,110,000 for four additional childcare rooms
  • Number of students: 501
  • Location: 3070 Stillmeadow Rd.
  • Architect: WalterFedy
  • General contractor: Fortis Construction
James L. Dunn Public School

The GECDSB built James L. Dunn Public School to help meet increased demands for French Immersion programming in the City of Windsor. This school replaced Giles Campus French Immersion Public School.

Construction began in November of 2019 and the school opened in September of 2022. 

  • Grant: $15,230,000
  • Number of students: 645
  • Architect: J.P. Thomson Architects

General contractor: Fortis ​Group

James L Dunn Exterior picture

 Legacy Oak Trail Public School (2021) + Addition (2024)

The Greater Essex County District School Board has built a new elementary school in LaSalle to replace Prince Andrew Public School.

Construction on the new school began in April of 2020 and finished in the summer of 2021 with the school opening in September 2021.

  • ​​​​​​Grant: $9,180,832
  • Number of students: 432
  • Architect: The WalterFedy Partnership Architects
  • General contractor: Rosati Construction

 Legacy Oak Front Exterior

 

Addition Details

  • Grant: $4,901,913
  • Pupil Places: 167 (5 classrooms and 2 full-day kindergarten)
  • Architect: Cornerstone WalterFedy
  • General Contractor: Front Construction
  • Construction Begins: July 2023
  • Occupancy: September 2024
North Star High School 

North Star High School consolidated General Amherst and Western Secondary. The school opened in September of 2022. 

  • Grant: $24,324,129
  • Number of students: 819
  • Architect: J.P. Thomson Ltd.
  • General contractor: Fortis Construction

North Start Highschool Exterior photo